Data date Week 32 Pay application 08
Forecast completion Week 63 Contract: week 60
Change this period +3 weeks Was on time last month
Critical path Switchgear Was interior finishes
What changed this period
Framing topped out on level 5 and roofing started on the east half. The switchgear manufacturer revised its ship date by ten weeks, to week 48.
What is driving completion
Switchgear delivery now controls permanent power, elevator inspection, commissioning and turnover. Interior finishes, critical last month, now have three weeks of float against the forecast date, and none against the contract date.
Decisions needed
- Authorize temporary power for equipment start-up — needed by week 34.
- Release the elevator installer to mobilize on temporary power.
- Confirm whether phased turnover by floor is acceptable to the owner.