CPM baseline schedules: Baseline schedules built to be accepted — and used.
A complete, logic-driven CPM baseline in Primavera P6 or Microsoft Project, built with your project team and checked against the contract’s scheduling specification before it is submitted.
Typical fee $4,000 – $5,000 per schedule See pricing

The short answer
What is a baseline schedule?
A baseline schedule is the project’s plan of record: a critical path method (CPM) model of how the work will be built from notice to proceed through substantial completion. Every activity has a duration and is tied by logic to what comes before and after it, so the software can calculate which sequence of work controls the finish date — the critical path.
Everything that follows is measured against it. Monthly updates, time-extension requests and any later delay analysis all start from the baseline, which is why owners review it closely and why it is worth getting right before work gathers pace.
What’s included
What the work covers.
Specification review
We read the scheduling specification, milestones, liquidated-damages clauses and phasing requirements first, so the schedule is built to the contract instead of corrected to it.
Sequencing with your team
A working session with your project manager, superintendent and key subcontractors sets the construction approach. The schedule reflects how they intend to build.
Complete logic, realistic durations
Every activity has a predecessor and a successor, constraints are used sparingly, and durations come from quantities and crew flow — not from the end date.
Procurement tied to installation
Submittals, approvals, fabrication and delivery for long-lead items are linked to the work they feed, so a late release shows up as a late finish.
Calendars, weather and coding
Work calendars, holidays and anticipated weather days per the contract, plus activity codes for area, phase, trade and responsibility.
Cost and resource loading
Where the contract asks for it, activities carry cost and labor so the schedule produces cash-flow curves and supports pay applications.
Quality control
What “checked before it is submitted” means.
Checks we run before a baseline goes out
Illustrative example
| Check | What we look for | Why it matters |
|---|---|---|
| Open ends | Every activity except the first and last has a predecessor and a successor | Missing logic hides the true critical path |
| Constraints | Date constraints limited to contract milestones | Hard constraints override logic and distort float |
| Lags and leads | Lags short and explained; no negative lags | Hidden time belongs in an activity people can see |
| Durations | Long activities broken down, apart from procurement | Detail makes progress measurable |
| Float | High-float activities reviewed for missing ties | Excess float usually means missing logic |
| Critical path | One continuous path that makes construction sense | It is the first thing a reviewer reads |
| Calendars | Work weeks, holidays and weather allowance per the contract | Calendars change every calculated date |
| Procurement | Long-lead items tied to the work they feed | Late buyout is a common cause of late finishes |
| Contract dates | Milestones, phasing and access limits match the contract | The baseline becomes the yardstick for time |
How it works
From first call to delivery.
Kick off and gather
We collect the contract, drawings, estimate and any bid schedule, and agree on the submittal date.
Sequence the work
A working session with the people who will run the job sets phasing, crew flow and key durations.
Build and check
We build the network, calculate the critical path and run quality checks for open ends, constraints, lags and float.
Review with the team
Your team reviews a draft in plain layouts. We revise until it is a plan they will stand behind.
Submit and respond
We prepare the submittal package and respond to reviewer comments through acceptance.
Deliverables
What you receive
- Native schedule file (Primavera P6 .xer or Microsoft Project .mpp)
- Full Gantt layout organized by work breakdown structure, as PDF
- Critical path (longest path) and milestone summary layouts
- Basis-of-schedule narrative: assumptions, calendars, constraints and critical path
- Cost- or resource-loading reports and cash-flow curve, when required
- Written responses to reviewer comments
To get started
What we need from you
- Contract, general conditions and the scheduling specification
- Drawings, phasing and logistics plans
- Estimate or schedule of values
- Subcontractor durations and lead times for long-lead items
- Time with your project manager and superintendent for a working session
Common questions
Questions, answered.
How much does a baseline schedule cost?
For a typical commercial, mixed-use or multifamily project, $4,000 to $5,000, fixed in writing before we start. Large, phased or cost-loaded schedules are quoted individually. See our pricing page for what is included.
How long does it take to build a baseline schedule?
It depends on the size of the project and how quickly the team can give input. Most of the calendar time goes to the team’s review, not the modeling. We agree on the submittal date at kickoff and plan backward from it.
Primavera P6 or Microsoft Project?
Whichever the contract requires. If it is silent, we recommend one based on the size of the job, who needs to open the file, and whether cost loading or multiple calendars are involved. We work in both.
The owner rejected our baseline. Can you fix it?
Usually, yes. We start with the reviewer’s comments and a health check of the file, correct the logic, constraints or missing scope behind the rejection, and resubmit with a response to each comment.
Who owns the schedule?
You do. You receive the native file with every submittal, and the plan is your team’s plan. We build and maintain the model.
Related services
Often paired with
Schedule updates & reporting
Your schedule statused against real progress every period, with a plain-English report on what changed and what it affects.
Look-ahead schedules
Three- and six-week look-aheads tied to the CPM schedule and written for the superintendent and the trades.
Bid & preconstruction schedules
Proposal schedules, duration checks, cost loading and cash-flow curves — before the contract dates are locked in.
Further reading
From our guides
Baseline schedule review checklist
A practical checklist for building or reviewing a construction baseline schedule: scope, logic, constraints, durations, float, calendars and critical path.
Weather days in a construction schedule
How to plan for normal weather in a baseline schedule, record weather days during the job, and show when unusually severe weather supports a time extension.
Cost-loaded schedules, explained
What a cost-loaded construction schedule is, who requires one, how to build it from the schedule of values, how it drives pay applications, and common mistakes.
What is a CPM schedule?
A plain-English guide to CPM scheduling in construction: activities, logic, the forward and backward pass, float and the critical path, with an example.