Recovery schedules: Behind schedule? See the real options.
When an update shows the finish date slipping, we find what is driving it, model the ways back, and give you a recovery schedule the team can deliver and the owner can accept.
Typical fee $2,500 – $4,000 See pricing

The short answer
What is a recovery schedule?
A recovery schedule shows how a project that has fallen behind will regain its contract dates — or get as close as is realistic — by resequencing work, adding crews or shifts, overlapping activities or re-phasing turnover. Many contracts require one once the forecast completion slips past a set threshold.
The risk with recovery schedules is wishful thinking: durations shortened on paper with no plan behind them. A credible one starts from an honest diagnosis, tests each option against crew sizes, access and inspections, and states plainly what each recovery measure requires.
What’s included
What the work covers.
Diagnosis
We trace the slip to the activities and events that caused it, using the updates and the project record.
Resequencing options
Changes in work flow — by floor, area or trade — that gain time without adding cost, tested for trade stacking and access.
Added-resource options
Extra crews, extended shifts or weekend work, modeled only where they sit on the critical path and will actually move the date.
Procurement and temporary measures
Alternates, expediting, partial deliveries and temporary systems that take a late item off the critical path.
Side-by-side comparison
Each option is shown with the time it recovers, what it takes and what could go wrong, so the decision is an informed one.
Tracking
Recovery activities are flagged and checked in each look-ahead and update until the time is back.
Sample deliverable
The options side by side, trade-offs included.
Recovery options compared
Illustrative example
| Option | Time recovered | What it takes | Watch for |
|---|---|---|---|
| Equipment start-up on temporary power | 2–3 weeks | Temporary service or generator; inspector acceptance | Steps that still need permanent power |
| Commissioning overlapped with final inspections | About 1 week | A system-by-system sequence agreed with the commissioning agent and the inspectors | No room to retest a system that fails |
| Saturday shifts to set and terminate the gear | A few days | Premium time for the electrical crew | Crew fatigue; inspections on weekdays only |
| Phased turnover by floor | Earlier use of lower floors | Owner and building-official agreement | Life-safety systems must be complete |
How it works
From first call to delivery.
Check the current schedule
We confirm the latest update is sound, so the recovery is built on a true starting point.
Find the drivers
Critical and near-critical paths are traced to the specific activities holding the date.
Work the options
A session with your project manager, superintendent and key trades generates realistic measures.
Model and compare
Each option is built into the schedule and its effect on completion is measured.
Issue and track
You receive the recovery schedule and narrative, then regular tracking against it.
Deliverables
What you receive
- Recovery schedule in native format (.xer or .mpp)
- Narrative describing causes, measures and assumptions
- Options comparison with time recovered by measure
- Before-and-after critical path layouts
- Tracking view for recovery activities
To get started
What we need from you
- The current schedule update and the baseline
- The cause of the slippage as the team understands it
- Subcontractor capacity for added crews or shifts
- Status of procurement and outstanding approvals
- Any owner correspondence requesting recovery
Common questions
Questions, answered.
How much does a recovery schedule cost?
Typically $2,500 to $4,000, depending on the condition of the current schedule and the number of options to model. You receive a fixed quote first. See our pricing page.
What is the difference between recovery and acceleration?
Recovery is the contractor making up time it is responsible for, generally at its own cost. Acceleration is finishing earlier than the contract, as properly extended, requires — usually at the owner’s direction, or because a time extension that was owed was not granted. The schedules can look alike; who pays depends on the contract and on who caused the delay.
Can every late project be recovered?
No. Sometimes the honest answer is a revised completion date with the reasons behind it. We show what is achievable, what it takes, and where the remaining exposure sits.
Will the owner accept our recovery schedule?
Owners accept recovery schedules that are specific. We show the measures as real activities with logic and resources behind them, not as shortened durations, and explain each one in the narrative.
We didn’t cause the delay. Do we still need a recovery schedule?
Check your contract and its notice requirements first. Where a delay is someone else’s responsibility, the usual route is a time impact analysis and a request for a time extension. We can prepare both, and keep the record clear about which days are being recovered and which are being claimed.
Related services
Often paired with
Schedule updates & reporting
Your schedule statused against real progress every period, with a plain-English report on what changed and what it affects.
Time impact analysis & claims support
Fragnets and before-and-after analysis for change orders and delays, time-extension requests and schedule support for claims.
Look-ahead schedules
Three- and six-week look-aheads tied to the CPM schedule and written for the superintendent and the trades.
Further reading
From our guides
Recovery schedule vs. acceleration
Recovery and acceleration both mean finishing sooner than the current forecast. The difference is who caused the delay — and that usually decides who pays.
How to read a schedule update
A guide for owners and project managers: eight questions that show whether a monthly schedule update is telling the truth about progress and the finish.