Schedule updates & reporting: Monthly updates that explain what changed and why.
We status your CPM schedule against real progress every period, recalculate the path to completion, and report it in plain English — so the finish date never moves without a reason attached.
Typical fee $1,750 per month See pricing

The short answer
What is a schedule update?
A schedule update records what actually happened since the last data date — actual starts and finishes, remaining durations, added or changed work — and recalculates the path to completion. It is usually required monthly, alongside the pay application.
A good update is more than progressed bars. It tells you whether the forecast completion date moved, which activities moved it, how much float the near-critical work has left, and which decisions are needed in the next few weeks to protect the finish.
What’s included
What the work covers.
Progress collection
A short standing call with your superintendent or project manager captures actual dates, remaining durations and what is coming next. Daily reports and photos fill the gaps.
Logic kept honest
Out-of-sequence progress is corrected, logic changes are documented, and the plan for remaining work is confirmed with the field instead of assumed.
Critical path analysis
Each period we identify the critical and near-critical paths, compare them with last month, and explain any shift.
Variance reporting
Milestones and key activities are compared with the baseline and the previous update, so slippage shows up as a trend and not as a surprise.
Change and delay tracking
Change orders, RFIs and other events with schedule impact are logged as they happen — the contemporaneous record that supports a later time extension.
Narrative report
A short written report: where the job stands, what changed, what is driving completion, and what needs a decision.
Sample deliverable
A report your team will actually read.
Schedule narrative — Update 08
Illustrative example
Data date Week 32 Pay application 08
Forecast completion Week 63 Contract: week 60
Change this period +3 weeks Was on time last month
Critical path Switchgear Was interior finishes
What changed this period
Framing topped out on level 5 and roofing started on the east half. The switchgear manufacturer revised its ship date by ten weeks, to week 48.
What is driving completion
Switchgear delivery now controls permanent power, elevator inspection, commissioning and turnover. Interior finishes, critical last month, now have three weeks of float against the forecast date, and none against the contract date.
Decisions needed
- Authorize temporary power for equipment start-up — needed by week 34.
- Release the elevator installer to mobilize on temporary power.
- Confirm whether phased turnover by floor is acceptable to the owner.
How it works
From first call to delivery.
Set the data date
We agree on a cutoff date each period, usually tied to the pay application.
Collect progress
A short call with the field, backed by daily reports, captures what was done and what has changed.
Update and analyze
We status the schedule, recalculate, and review the critical path, float and milestone variances.
Review the draft
Your project manager sees the results before anyone else, with time to respond.
Issue the package
You receive the native file, layouts and narrative, ready to submit.
Deliverables
What you receive
- Updated native schedule file (.xer or .mpp)
- Gantt layouts showing current dates against the baseline
- Critical and near-critical path report
- Milestone variance report: baseline, last update and current forecast
- Written narrative with changes, delays and decisions needed
- Cash-flow or earned-value reports, when the schedule is cost-loaded
To get started
What we need from you
- Actual start and finish dates and remaining durations, or daily reports
- Change orders, RFIs and directives that affect time
- Submittal and procurement status for long-lead items
- Weather and other delay records
- A short call each period with the field
Common questions
Questions, answered.
How much do monthly schedule updates cost?
$1,750 a month for one project updated monthly, including the narrative and the files ready to submit. See our pricing page for what is included and what changes the figure.
How often should a construction schedule be updated?
Monthly is the contractual norm, tied to the pay application. Fast or troubled projects often benefit from a mid-month check or a weekly look-ahead between formal updates.
Can you take over a schedule someone else built?
Yes. We start with a health check of the file — logic, constraints, calendars and update history — and tell you what we found before we take it forward.
Do you need to be on site?
Usually not. Most update work is done remotely with a standing call, daily reports and photos, which is how we support projects nationwide. Site visits are arranged when a walk-through adds value.
What if the update shows we are behind?
Then you hear it from us first, with the cause and the options. If the contract calls for it, we prepare a recovery schedule. If someone else caused the delay, we help you document it for a time extension.
Related services
Often paired with
Look-ahead schedules
Three- and six-week look-aheads tied to the CPM schedule and written for the superintendent and the trades.
Recovery schedules
When the finish date slips: what is driving it, the realistic ways back, and a recovery plan the owner can accept.
Time impact analysis & claims support
Fragnets and before-and-after analysis for change orders and delays, time-extension requests and schedule support for claims.
Further reading
From our guides
How to read a schedule update
A guide for owners and project managers: eight questions that show whether a monthly schedule update is telling the truth about progress and the finish.
The schedule narrative: example and outline
What a construction schedule narrative is, what owners expect at baseline and at each monthly update, a full written example, and a reusable outline.
Retained logic vs. progress override
What retained logic and progress override do to out-of-sequence work in Primavera P6, a worked example, which one specifications require, and the better fix.