Look-ahead schedules: Look-aheads that connect the plan to this week’s work.
Three- and six-week look-ahead schedules, tied to your CPM schedule and written for superintendents and foremen — so the field and the master schedule tell the same story.
Typical fee $800 – $1,200 a month See pricing

The short answer
What is a look-ahead schedule?
A look-ahead schedule is a short-interval plan, usually covering the next three weeks, that breaks CPM activities into the day-by-day work each crew will perform. It is the working document for the weekly subcontractor coordination meeting.
The CPM schedule answers “when does this phase happen, and what does it affect?” The look-ahead answers “who is working where on Tuesday, and what has to be in place for that to happen?” The two should be tied together. When they drift apart, the monthly update stops describing the real job.
What’s included
What the work covers.
Tied to the CPM schedule
Look-ahead tasks roll up to CPM activity IDs, so weekly progress flows into the monthly update and the critical path stays visible in the field.
Day by day, by area and trade
Tasks are broken down to crew and location, with working days shown — the level of detail foremen actually plan at.
Constraint screening
For each upcoming task we track what must be in place first: RFIs, approved submittals, materials, inspections, access and preceding work.
Six-week make-ready view
A longer look catches procurement, inspections and prerequisites while there is still time to act.
Planned versus actual
Last week’s plan is checked against what was done, with the reasons for misses — the quickest way to make the next plan more reliable.
Built for the field
Clean, large-format PDFs or spreadsheets that read well on a phone, a tablet or the trailer wall.
Sample deliverable
The plan for the next fifteen working days.
Three-week look-ahead — Level 3 and roof
Illustrative example
| Task | Trade | Week 1 | Week 2 | Week 3 | Needs first | ||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Week 1 day 1 | Week 1 day 2 | Week 1 day 3 | Week 1 day 4 | Week 1 day 5 | Week 2 day 1 | Week 2 day 2 | Week 2 day 3 | Week 2 day 4 | Week 2 day 5 | Week 3 day 1 | Week 3 day 2 | Week 3 day 3 | Week 3 day 4 | Week 3 day 5 | |||
| L3 east — frame walls | Framing | Working | Working | Working | Working | Working | — | ||||||||||
| L3 east — MEP rough-in | MEP trades | Working | Working | Working | Working | Working | Working | RFI 114 answer needed | |||||||||
| L3 east — in-wall inspection | Inspector | Working | Book by Wednesday | ||||||||||||||
| L3 east — insulation | Insulation | Working | Working | — | |||||||||||||
| L3 east — hang drywall | Drywall | Working | Working | Working | Board delivery Tue, week 2 | ||||||||||||
| Roof — membrane, east half Critical | Roofing | Working | Working | Working | Working | Working | Working | Working | Working | Weather | |||||||
| Level 2 — window install Critical | Glazing | Working | Working | Working | Working | Working | Working | Working | Working | Delivery confirmed | |||||||
Free download
This look-ahead, as an Excel template
Run your own in the same format: bars that draw themselves, a constraint log on every row and a column for the CPM activity ID.
How it works
From first call to delivery.
Collect
A short weekly call with the superintendent captures progress and next week’s intent.
Draft
We update the look-ahead, screen constraints and flag anything touching the critical path.
Issue
The look-ahead goes out ahead of the coordination meeting.
Meet and commit
Your team runs the meeting from it; trades confirm or adjust their dates.
Feed the update
Weekly actuals carry into the monthly CPM update.
Deliverables
What you receive
- Three-week look-ahead by area and trade, issued weekly
- Constraint log with owners and need-by dates
- Planned-versus-actual summary for the prior week
- Optional six-week make-ready view
- Progress data ready for the monthly update
To get started
What we need from you
- The current CPM schedule (or we build one)
- A weekly call with the superintendent
- Subcontractor commitments from the coordination meeting
- Delivery, inspection and RFI status
Common questions
Questions, answered.
How much does a look-ahead schedule service cost?
A weekly three-week look-ahead typically runs $800 to $1,200 a month, depending on the number of areas and trades. It can run on its own or alongside a monthly update package. See our pricing page.
Why not just filter the CPM schedule to the next three weeks?
Because CPM activities are usually too coarse to run a crew from. “Level 3 MEP rough-in, 20 days” is right for the master schedule; the field needs to know which trade is in which corridor on which day.
Is this the same as pull planning or the Last Planner System?
It shares the same core ideas: make work ready before it starts, and get commitments from the people doing it. A constraint-screened look-ahead works with or without a formal pull-planning program.
Who updates it each week?
We do, from a short call with your superintendent. The plan stays theirs — we keep it current, formatted and consistent with the CPM schedule.
How is a look-ahead different from a schedule update?
The look-ahead is weekly, short-range and written for the field. The update is typically monthly, covers the whole project and is written for the contract. Done together, each makes the other more accurate.
Do you have a look-ahead template we can use ourselves?
Yes. Our three-week look-ahead template is a free Excel workbook in the format shown on this page, and our look-ahead guide explains how to run one. If you would rather have it kept current every week and tied to the CPM schedule, that is what this service does.
Related services
Often paired with
Schedule updates & reporting
Your schedule statused against real progress every period, with a plain-English report on what changed and what it affects.
CPM baseline schedules
A complete, logic-driven plan of record, built with your team and checked against the specification before it is submitted.
Recovery schedules
When the finish date slips: what is driving it, the realistic ways back, and a recovery plan the owner can accept.
Further reading
From our guides
How to build a 3-week look-ahead
How to build a three-week look-ahead schedule from your CPM schedule and run the weekly meeting from it. Includes a free Excel look-ahead template.
How to read a schedule update
A guide for owners and project managers: eight questions that show whether a monthly schedule update is telling the truth about progress and the finish.