The short answer

What is a look-ahead schedule?

A look-ahead schedule is a short-interval plan, usually covering the next three weeks, that breaks CPM activities into the day-by-day work each crew will perform. It is the working document for the weekly subcontractor coordination meeting.

The CPM schedule answers “when does this phase happen, and what does it affect?” The look-ahead answers “who is working where on Tuesday, and what has to be in place for that to happen?” The two should be tied together. When they drift apart, the monthly update stops describing the real job.

What’s included

What the work covers.

Tied to the CPM schedule

Look-ahead tasks roll up to CPM activity IDs, so weekly progress flows into the monthly update and the critical path stays visible in the field.

Day by day, by area and trade

Tasks are broken down to crew and location, with working days shown — the level of detail foremen actually plan at.

Constraint screening

For each upcoming task we track what must be in place first: RFIs, approved submittals, materials, inspections, access and preceding work.

Six-week make-ready view

A longer look catches procurement, inspections and prerequisites while there is still time to act.

Planned versus actual

Last week’s plan is checked against what was done, with the reasons for misses — the quickest way to make the next plan more reliable.

Built for the field

Clean, large-format PDFs or spreadsheets that read well on a phone, a tablet or the trailer wall.

Sample deliverable

The plan for the next fifteen working days.

Three-week look-ahead — Level 3 and roof

Illustrative example

Task Trade Week 1 Week 2 Week 3 Needs first
Week 1 day 1 Week 1 day 2 Week 1 day 3 Week 1 day 4 Week 1 day 5 Week 2 day 1 Week 2 day 2 Week 2 day 3 Week 2 day 4 Week 2 day 5 Week 3 day 1 Week 3 day 2 Week 3 day 3 Week 3 day 4 Week 3 day 5
L3 east — frame wallsFramingWorkingWorkingWorkingWorkingWorking—
L3 east — MEP rough-inMEP tradesWorkingWorkingWorkingWorkingWorkingWorkingRFI 114 answer needed
L3 east — in-wall inspectionInspectorWorkingBook by Wednesday
L3 east — insulationInsulationWorkingWorking—
L3 east — hang drywallDrywallWorkingWorkingWorkingBoard delivery Tue, week 2
Roof — membrane, east half CriticalRoofingWorkingWorkingWorkingWorkingWorkingWorkingWorkingWorkingWeather
Level 2 — window install CriticalGlazingWorkingWorkingWorkingWorkingWorkingWorkingWorkingWorkingDelivery confirmed

Free download

This look-ahead, as an Excel template

Run your own in the same format: bars that draw themselves, a constraint log on every row and a column for the CPM activity ID.

Download the template

Excel workbook (.xlsx) · 16 KB · No sign-up · What is inside

How it works

From first call to delivery.

  1. Collect

    A short weekly call with the superintendent captures progress and next week’s intent.

  2. Draft

    We update the look-ahead, screen constraints and flag anything touching the critical path.

  3. Issue

    The look-ahead goes out ahead of the coordination meeting.

  4. Meet and commit

    Your team runs the meeting from it; trades confirm or adjust their dates.

  5. Feed the update

    Weekly actuals carry into the monthly CPM update.

Deliverables

What you receive

  • Three-week look-ahead by area and trade, issued weekly
  • Constraint log with owners and need-by dates
  • Planned-versus-actual summary for the prior week
  • Optional six-week make-ready view
  • Progress data ready for the monthly update

To get started

What we need from you

  • The current CPM schedule (or we build one)
  • A weekly call with the superintendent
  • Subcontractor commitments from the coordination meeting
  • Delivery, inspection and RFI status

Common questions

Questions, answered.

How much does a look-ahead schedule service cost?

A weekly three-week look-ahead typically runs $800 to $1,200 a month, depending on the number of areas and trades. It can run on its own or alongside a monthly update package. See our pricing page.

Why not just filter the CPM schedule to the next three weeks?

Because CPM activities are usually too coarse to run a crew from. “Level 3 MEP rough-in, 20 days” is right for the master schedule; the field needs to know which trade is in which corridor on which day.

Is this the same as pull planning or the Last Planner System?

It shares the same core ideas: make work ready before it starts, and get commitments from the people doing it. A constraint-screened look-ahead works with or without a formal pull-planning program.

Who updates it each week?

We do, from a short call with your superintendent. The plan stays theirs — we keep it current, formatted and consistent with the CPM schedule.

How is a look-ahead different from a schedule update?

The look-ahead is weekly, short-range and written for the field. The update is typically monthly, covers the whole project and is written for the contract. Done together, each makes the other more accurate.

Do you have a look-ahead template we can use ourselves?

Yes. Our three-week look-ahead template is a free Excel workbook in the format shown on this page, and our look-ahead guide explains how to run one. If you would rather have it kept current every week and tied to the CPM schedule, that is what this service does.

Free 30-minute consultation

Bring your schedule, your spec or just your questions.

Thirty minutes with a scheduler, no obligation. We will look at where your project stands and tell you plainly what would help.

Call Free consultation