Delay analysis: What delayed the project, by how much, and why.

A structured, evidence-based analysis of schedule delay — for time extensions, claims, liquidated-damages disputes and early case assessment, on behalf of contractors or owners.

Typical fee From $10,000 See pricing

A flat roof with white membrane going down under an overcast sky

The short answer

What is delay analysis?

Delay analysis is the forensic side of scheduling: a structured look back through the schedules and the project record to establish which events delayed completion, by how many days, and who was responsible for each.

It is the factual basis for time extensions, delay claims and the assessment — or defense — of liquidated damages. The right method depends on the contract, the quality of the schedules and the records available, which is why the first step is always an honest look at what the evidence can support.

What’s included

What the work covers.

Records review

Baseline, updates, daily reports, RFIs, submittals, change orders, meeting minutes, correspondence and weather records.

Schedule validation

We test whether the baseline and updates are reliable enough to analyze from, and document any corrections.

As-built reconstruction

Actual start and finish dates are established from the record, independent of what any one schedule says.

Method selection

As-planned versus as-built, windows analysis, time impact analysis or collapsed as-built — chosen to fit the contract and the available data.

Causation and concurrency

Critical delays are identified period by period and tied to specific events, with concurrent and pacing delays assessed.

Report and exhibits

A written report with clear graphics showing what moved the completion date, when, and by how much.

Choosing a method

The method follows the evidence.

Delay analysis methods at a glance

Illustrative example

MethodHow it worksFits best when
As-planned vs. as-builtCompares the baseline plan with what was actually built, activity by activity.The schedule was rarely updated, but good as-built records exist.
Windows analysisSteps through the job one update period at a time, measuring how the critical path and completion date moved in each.Regular, reliable updates were kept through the job.
Time impact analysisInserts a fragnet for each event into the schedule current at the time and measures the change in completion.Delays are evaluated as they happen, or the contract requires it.
Collapsed as-builtStarts from the as-built schedule and removes delay events to show when the work would have finished without them.Detailed as-built data exists but contemporaneous updates do not.

How it works

From first call to delivery.

  1. Initial assessment

    We review the key documents and tell you what the record is likely to support, before a large budget is committed.

  2. Agree on scope and method

    The questions to answer, the method and the deliverables are set with you and your counsel.

  3. Build the as-built record

    Dates and events are assembled and cross-checked across sources.

  4. Analyze

    Delay is measured period by period along the critical path and attributed to its causes.

  5. Report and support

    Findings are delivered in writing and supported through negotiation or mediation.

Deliverables

What you receive

  • Written delay analysis report
  • Period-by-period summary of critical delay and its causes
  • As-built schedule and supporting chronology
  • Graphic exhibits comparing planned and actual progress
  • Native schedule files used in the analysis

To get started

What we need from you

  • Baseline and all schedule updates, in native format where they exist
  • Daily reports, meeting minutes and progress photos
  • RFI, submittal and change order logs
  • Notices and correspondence about delay
  • The contract provisions on time, delay and damages

Common questions

Questions, answered.

How much does a delay analysis cost?

Delay analysis is billed at $175 an hour against a budget agreed in advance. Most assignments start at around $10,000, and the total depends on the length of the project and the records available. See our pricing page.

Which delay analysis method is best?

There isn’t a single best method. The contract may name one, and the available schedules and records limit what can be done reliably. AACE International’s Recommended Practice 29R-03 describes the recognized methods; we recommend the one the evidence will support.

What if the schedule was never properly updated?

Analysis is still possible, but it leans harder on the as-built record: daily reports, photos, inspection records and correspondence. We tell you early how far the available evidence can go.

What is concurrent delay?

Two or more independent delays that affect the critical path in the same period, where each alone would have delayed completion — typically one the owner is responsible for and one the contractor is. How concurrency is treated depends on the contract and the governing law.

Do you work for contractors or owners?

Both. The analysis follows the same method and the same evidence whichever side asks for it.

Do you work with attorneys?

Yes. Delay analysis often runs alongside legal advice. Our role is the schedule and the facts; questions of legal entitlement belong to your counsel.

Free 30-minute consultation

Bring your schedule, your spec or just your questions.

Thirty minutes with a scheduler, no obligation. We will look at where your project stands and tell you plainly what would help.

Call Free consultation