Construction scheduling glossary: The language of schedules, in plain English.
54 terms you will meet in schedule narratives, specifications and delay claims — each defined in a sentence or two.
A
- Activity
- A defined piece of work in a schedule, with a duration, logic ties to other activities and usually a responsible party.
- Activity ID
- The unique identifier of an activity. Stable IDs allow one update to be compared with the next.
- Actual dates
- The dates on which an activity really started and finished, recorded when the schedule is updated.
- As-built schedule
- A schedule showing when work was actually performed, assembled from actual dates and project records.
- As-planned vs. as-built
- A delay analysis method that compares the baseline plan with what actually happened, activity by activity. Delay analysis
B
- Backward pass
- The part of the CPM calculation that works from the end of the schedule back to the start, finding the latest each activity can start and finish.
- Baseline schedule
- The accepted plan of record for a project, against which progress, changes and delays are measured. CPM baseline schedules
- Basis of schedule
- The narrative that documents the assumptions behind a baseline: calendars, durations, sequence, constraints and the critical path. Schedule narrative example
C
- Calendar
- The definition of working and non-working time applied to an activity, such as a five-day week with holidays.
- Concurrent delay
- Two or more independent delays that affect the critical path in the same period, each of which would have delayed completion on its own. Delay analysis
- Constraint
- A date restriction placed on an activity that limits or overrides what the logic would otherwise calculate.
- Cost loading
- Assigning contract value to schedule activities so the schedule can forecast billings and cash flow. Cost-loaded schedules, explained
- CPM (critical path method)
- A scheduling technique that calculates dates from activity durations and logic, and identifies the longest chain of dependent work. What is a CPM schedule?
- Critical path
- The longest chain of linked activities through a schedule. It sets the earliest possible completion date, and a delay on it delays the project.
D
- Data date
- The cutoff date of a schedule update. Progress before it is recorded as actual; everything after it is forecast.
- DCMA 14-point assessment
- A set of schedule quality checks from the US Defense Contract Management Agency, widely used as a health check on any CPM schedule. Baseline schedule checklist
- Delay analysis
- A structured review of schedules and records to establish what delayed completion, by how much, and who was responsible. Delay analysis
- Duration
- The working time an activity takes. Original duration is the plan; remaining duration is what is left at the data date.
E
- Early dates
- The earliest an activity can start and finish, calculated by the forward pass.
- Earned value
- A way of measuring progress by comparing the budgeted value of work performed with the plan and with actual cost.
- Excusable delay
- A delay for which the contract grants more time, typically because it was outside the contractor’s control. It is compensable if money is due as well.
F
- Float (total float)
- The amount of time an activity can slip without delaying project completion. Who owns the float?
- Forward pass
- The part of the CPM calculation that works from the start of the schedule to the end, finding the earliest each activity can start and finish.
- Fragnet
- A small group of linked activities representing a change or delay, inserted into a schedule to measure its effect. Time impact analysis explained
- Free float
- The amount of time an activity can slip without delaying the early start of any activity that follows it.
L
- Lag
- Waiting time added to a relationship, such as curing time between pouring concrete and stripping forms.
- Late dates
- The latest an activity can start and finish without delaying completion, calculated by the backward pass.
- Lead
- A negative lag, which lets a successor start before its predecessor finishes. Most specifications discourage or prohibit it.
- Level of effort
- An activity, such as supervision, whose duration is set by the work it spans instead of by its own scope.
- Liquidated damages
- A daily amount agreed in the contract that the contractor owes the owner for each day of late completion.
- Logic
- The relationships between activities: finish-to-start, start-to-start, finish-to-finish and, rarely, start-to-finish.
- Longest path
- The critical path defined as the longest continuous chain of activities to project completion, regardless of float values.
- Look-ahead schedule
- A short-interval schedule, usually three weeks, showing day-by-day work by area and trade. Look-ahead schedules
M
- Milestone
- An activity with no duration that marks a key event, such as notice to proceed or substantial completion.
N
- Near-critical path
- A chain of activities with very little float, which a small delay would make critical.
- Negative float
- Float below zero. It shows by how much the schedule misses a constrained or contract date.
- Notice to proceed (NTP)
- The owner’s written authorization to start work. Contract time normally runs from it.
O
- Open end
- An activity with no predecessor or no successor. Open ends hide the true critical path.
- Out-of-sequence progress
- Work reported as started or finished before the logic says its predecessors are complete. Retained logic vs. progress override
P
- Pacing delay
- A deliberate slowing of work by one party because another party’s delay has already made finishing sooner pointless.
- Predecessor and successor
- A predecessor is an activity that must start or finish before another can; the dependent activity is its successor.
R
- Recovery schedule
- A schedule showing how a project that has fallen behind will regain its contract dates. Recovery schedules
- Resource loading
- Assigning labor, equipment or materials to activities so the schedule can show staffing levels over time.
- Retained logic and progress override
- Two settings for handling out-of-sequence progress. Retained logic makes remaining work wait for its predecessors; progress override ignores the broken link. Retained logic vs. progress override
S
- S-curve
- A graph of cumulative cost or progress over time, named for its shape: slow at the start, steep in the middle, flattening at the end.
- Schedule narrative
- The written report submitted with a schedule that explains progress, changes, the critical path and risks. Schedule narrative example
- Schedule of values
- The breakdown of the contract sum into items used as the basis for progress payments. Cost-loaded schedules, explained
- Schedule update
- A periodic statusing of the schedule that records actual progress to the data date and recalculates the forecast. Schedule updates & reporting
- Substantial completion
- The stage at which the work is complete enough for the owner to use it as intended. It usually ends exposure to liquidated damages.
T
- Time impact analysis (TIA)
- A method that measures the effect of a change or delay by inserting a fragnet into the current schedule and comparing completion dates. Time impact analysis
W
- Weather day
- A day on which weather prevents work on the controlling activity. Contracts usually state how many are expected and how extra ones are handled. Weather days in a construction schedule
- Windows analysis
- A retrospective delay analysis method that steps through a project one update period at a time, measuring how completion moved in each. Delay analysis
- Work breakdown structure (WBS)
- A hierarchy that organizes a schedule by area, phase or deliverable, so it can be summarized and filtered.
X
- XER file
- The export format of Primavera P6. It contains the full schedule: activities, logic, calendars, resources and codes. Primavera P6 scheduling