Construction scheduling glossary: The language of schedules, in plain English.

54 terms you will meet in schedule narratives, specifications and delay claims — each defined in a sentence or two.

A

Activity
A defined piece of work in a schedule, with a duration, logic ties to other activities and usually a responsible party.
Activity ID
The unique identifier of an activity. Stable IDs allow one update to be compared with the next.
Actual dates
The dates on which an activity really started and finished, recorded when the schedule is updated.
As-built schedule
A schedule showing when work was actually performed, assembled from actual dates and project records.
As-planned vs. as-built
A delay analysis method that compares the baseline plan with what actually happened, activity by activity. Delay analysis

B

Backward pass
The part of the CPM calculation that works from the end of the schedule back to the start, finding the latest each activity can start and finish.
Baseline schedule
The accepted plan of record for a project, against which progress, changes and delays are measured. CPM baseline schedules
Basis of schedule
The narrative that documents the assumptions behind a baseline: calendars, durations, sequence, constraints and the critical path. Schedule narrative example

C

Calendar
The definition of working and non-working time applied to an activity, such as a five-day week with holidays.
Concurrent delay
Two or more independent delays that affect the critical path in the same period, each of which would have delayed completion on its own. Delay analysis
Constraint
A date restriction placed on an activity that limits or overrides what the logic would otherwise calculate.
Cost loading
Assigning contract value to schedule activities so the schedule can forecast billings and cash flow. Cost-loaded schedules, explained
CPM (critical path method)
A scheduling technique that calculates dates from activity durations and logic, and identifies the longest chain of dependent work. What is a CPM schedule?
Critical path
The longest chain of linked activities through a schedule. It sets the earliest possible completion date, and a delay on it delays the project.

D

Data date
The cutoff date of a schedule update. Progress before it is recorded as actual; everything after it is forecast.
DCMA 14-point assessment
A set of schedule quality checks from the US Defense Contract Management Agency, widely used as a health check on any CPM schedule. Baseline schedule checklist
Delay analysis
A structured review of schedules and records to establish what delayed completion, by how much, and who was responsible. Delay analysis
Duration
The working time an activity takes. Original duration is the plan; remaining duration is what is left at the data date.

E

Early dates
The earliest an activity can start and finish, calculated by the forward pass.
Earned value
A way of measuring progress by comparing the budgeted value of work performed with the plan and with actual cost.
Excusable delay
A delay for which the contract grants more time, typically because it was outside the contractor’s control. It is compensable if money is due as well.

F

Float (total float)
The amount of time an activity can slip without delaying project completion. Who owns the float?
Forward pass
The part of the CPM calculation that works from the start of the schedule to the end, finding the earliest each activity can start and finish.
Fragnet
A small group of linked activities representing a change or delay, inserted into a schedule to measure its effect. Time impact analysis explained
Free float
The amount of time an activity can slip without delaying the early start of any activity that follows it.

L

Lag
Waiting time added to a relationship, such as curing time between pouring concrete and stripping forms.
Late dates
The latest an activity can start and finish without delaying completion, calculated by the backward pass.
Lead
A negative lag, which lets a successor start before its predecessor finishes. Most specifications discourage or prohibit it.
Level of effort
An activity, such as supervision, whose duration is set by the work it spans instead of by its own scope.
Liquidated damages
A daily amount agreed in the contract that the contractor owes the owner for each day of late completion.
Logic
The relationships between activities: finish-to-start, start-to-start, finish-to-finish and, rarely, start-to-finish.
Longest path
The critical path defined as the longest continuous chain of activities to project completion, regardless of float values.
Look-ahead schedule
A short-interval schedule, usually three weeks, showing day-by-day work by area and trade. Look-ahead schedules

M

Milestone
An activity with no duration that marks a key event, such as notice to proceed or substantial completion.

N

Near-critical path
A chain of activities with very little float, which a small delay would make critical.
Negative float
Float below zero. It shows by how much the schedule misses a constrained or contract date.
Notice to proceed (NTP)
The owner’s written authorization to start work. Contract time normally runs from it.

O

Open end
An activity with no predecessor or no successor. Open ends hide the true critical path.
Out-of-sequence progress
Work reported as started or finished before the logic says its predecessors are complete. Retained logic vs. progress override

P

Pacing delay
A deliberate slowing of work by one party because another party’s delay has already made finishing sooner pointless.
Predecessor and successor
A predecessor is an activity that must start or finish before another can; the dependent activity is its successor.

R

Recovery schedule
A schedule showing how a project that has fallen behind will regain its contract dates. Recovery schedules
Resource loading
Assigning labor, equipment or materials to activities so the schedule can show staffing levels over time.
Retained logic and progress override
Two settings for handling out-of-sequence progress. Retained logic makes remaining work wait for its predecessors; progress override ignores the broken link. Retained logic vs. progress override

S

S-curve
A graph of cumulative cost or progress over time, named for its shape: slow at the start, steep in the middle, flattening at the end.
Schedule narrative
The written report submitted with a schedule that explains progress, changes, the critical path and risks. Schedule narrative example
Schedule of values
The breakdown of the contract sum into items used as the basis for progress payments. Cost-loaded schedules, explained
Schedule update
A periodic statusing of the schedule that records actual progress to the data date and recalculates the forecast. Schedule updates & reporting
Substantial completion
The stage at which the work is complete enough for the owner to use it as intended. It usually ends exposure to liquidated damages.

T

Time impact analysis (TIA)
A method that measures the effect of a change or delay by inserting a fragnet into the current schedule and comparing completion dates. Time impact analysis

W

Weather day
A day on which weather prevents work on the controlling activity. Contracts usually state how many are expected and how extra ones are handled. Weather days in a construction schedule
Windows analysis
A retrospective delay analysis method that steps through a project one update period at a time, measuring how completion moved in each. Delay analysis
Work breakdown structure (WBS)
A hierarchy that organizes a schedule by area, phase or deliverable, so it can be summarized and filtered.

X

XER file
The export format of Primavera P6. It contains the full schedule: activities, logic, calendars, resources and codes. Primavera P6 scheduling