The short answer
What is a time impact analysis?
A time impact analysis (TIA) measures the effect of a specific change or delay on a project’s completion date. A small network of activities representing the event — a fragnet — is inserted into the most recent accepted schedule update, the schedule is recalculated, and the movement in the completion date is the time impact.
Most contracts that require CPM scheduling also require a TIA to support any request for more time, and most set short deadlines for giving notice. The analysis is strongest when it is prepared as the event unfolds, from the schedule that was current at the time.
What’s included
What the work covers.
Contract requirements check
We read the time-extension, notice and scheduling clauses first, so the analysis is prepared in the form the contract asks for.
The right starting schedule
The TIA is run in the last accepted update with a data date before the event began, validated before anything is added.
Fragnet development
The change or delay is modeled as activities with durations and logic, each supported by project documents.
Before-and-after analysis
Completion dates and critical paths are compared with and without the fragnet, and concurrent delays are checked.
Written narrative and exhibits
A clear account of the event, the method, the result and the supporting records — ready to attach to a change request.
Claims support
Chronologies, schedule exhibits and analysis for requests for equitable adjustment, negotiation and mediation, working alongside your counsel.
How it works
One change. One measured result.
How a time impact analysis measures a change
Illustrative example
1 · Accepted update, before the change Completion: March 12
2 · Same update, with the fragnet inserted Completion: March 26
14 calendar days The fragnet — redesign, resubmittal and the added work — is the only difference between the two runs, so the movement in completion is the time impact.
How it works
From first call to delivery.
Understand the event
What happened, when, and what the contract says about time and notice.
Validate the schedule
We confirm the update in effect when the event began is a sound basis for the analysis.
Build the fragnet
The team and the documents define the added or delayed work and how it ties into the schedule.
Insert and recalculate
The schedule is run with the fragnet and compared with the unimpacted version.
Report
You receive the narrative, exhibits and native files to submit, or to negotiate from.
Deliverables
What you receive
- TIA narrative with method, result and supporting references
- Fragnet layout showing the added activities and logic ties
- Before-and-after critical path and completion comparison
- Native schedule files for both versions
- For owners: a written evaluation with a recommended position
To get started
What we need from you
- The accepted baseline and updates, in native format
- Change documents: RFIs, bulletins, directives and pricing
- Daily reports, correspondence and photos covering the event
- The contract’s time-extension and notice provisions
Common questions
Questions, answered.
How much does a time impact analysis cost?
Typically $2,500 to $4,000 per event, depending on how well the event is documented. You receive a fixed quote before we start. See our pricing page.
What is a fragnet?
A fragnet (fragmentary network) is a small group of activities that represents a change or delay — for example redesign, re-approval, material delivery and the added work — together with the logic that ties it into the existing schedule.
When should a time impact analysis be prepared?
As early as possible. A prospective TIA, prepared when the change arises, forecasts the impact and lets time be settled with the change order. Waiting until the end of the job turns a simple analysis into a dispute about what the schedule showed months ago.
What if the delay isn’t on the critical path?
Then it uses float instead of moving the completion date, and a time extension is usually not due. It should still be documented: float is finite, and the next delay to the same path may be critical.
Do you prepare TIAs for owners as well as contractors?
Yes. We prepare them for contractors and review them for owners, developers and their representatives. The method is the same either way.
Is this legal advice?
No. We are scheduling consultants. We establish what the schedule and the record show, and we work alongside your attorney where entitlement turns on the contract or the law.
Related services
Often paired with
Delay analysis
A structured look back through the schedules and the record: what delayed completion, by how much, and who was responsible.
Schedule updates & reporting
Your schedule statused against real progress every period, with a plain-English report on what changed and what it affects.
Owner-side schedule review
An independent check of your contractor’s baseline and monthly updates, with written comments and a clear read on the finish date.
Further reading
From our guides
Time impact analysis, explained
What a time impact analysis is, when a contract requires one, how to build the fragnet step by step, a worked example, and the mistakes that get TIAs rejected.
Weather days in a construction schedule
How to plan for normal weather in a baseline schedule, record weather days during the job, and show when unusually severe weather supports a time extension.
Delay analysis methods compared
The main construction delay analysis methods compared: how each works, the schedules and records it needs, where it is weak, and how to choose between them.