Idaho Transportation Department
- A critical path method schedule in a format compatible with the current version of Microsoft Project
- Activity durations limited to 20 working days unless the Engineer allows otherwise
- Only contractual date constraints, and a work calendar defined for each activity
- A narrative covering major equipment, assumed production rates and how weather days were built in
- Float before substantial completion is shared on a first-come, first-served basis